‘A Very Good Team Effort’: District Officials Work Through Detailed Move-In Plan for Renovated, Expanded Saxe Middle School
|
District officials say teachers in Saxe Middle School’s art and music rooms have started packing up in boxes as they prepare on the final day of school (June 21) to vacate for a time so that extensive capital work can be completed this summer. Daniel Clarke, manager of facilities operations, told members of the Board of Education that his office is coordinating with construction company O&G Industries as well as the fire marshal to work within and even enhance a “very detailed, well-organized and thought-out plan” from Saxe Principal Greg Macedo. “It really has been a team effort to try and make this as efficient as possible,” Clarke told the Board of Ed during its meeting Monday, his first since taking over in the role from Bob Willoughby. “Because here we are in May and we say: ‘We are moving next month.’ When you say it that way, the urgency is there.”
The $18.6 million project is on time and budget, officials have said. To be completed for the start of next academic year, it includes the renovation of the 60-year-old auditorium at Saxe, as well as a “right-sizing” of music rooms that a building committee immediately identified as a need, and a 12-room addition that emerged a few months later to address rapidly rising enrollment at the overcrowded middle school.